Services
- Technical master planning of system groups 1 – 8 according to § 51 of HOAI (2009)
 
- Energy Concept
 
- Thermal simulation
 
- Performance phases 1 – 8
 
     
    
        Project scope
- Total costs: 32 million Euro
 
- TBE costs: 9.5 million Euro
 
- Main usage area modernization: 10,427 m²
 
- Main usage area new construction: 650 m²
 
     
 
    
        
    
Project description
    
        
    
- Building owner: Federal Ministry of Justice, Hessisches Baumanagement (HBM) (Hessian Building Management), northern location
 
- Architecture: Junk + Reich and Hartmann + Helm, Weimar
 
- Energy concept with thermal simulation, reduction in consumption approx. 30 %
 
- Up-to-date, complete fire protection technology 
 
- New construction of all sanitation rooms, water hygiene according to DIN 1988
 
- Replacement of complete heating system 900 kW, four ventilation systems with heat recovery -20.000 m³/h according to DDI 6022, refrigeration systems 150 kW
 
- Replacement of all electrical systems as well as transformer system, security lighting, energy-saving lighting, security technology according to guidelines of the BKA (Federal Crime Bureau), conference and interpreting systems, solar power system 45 KW, data and
 telecommunication system 
- Five freight and passenger elevators
 
- Comprehensive management system with 1,500 data points
 
- New construction of cafeteria serving 150 meals/day, gas-fired kitchen appliances, dish washing facility, serving counter, refrigeration facilities