New construction ADAC Head Office, Munich

Services

  • Technical master plan of system groups 1 –8 according §51 HOAI (2009), performance phases 2 –7

Project results

  • 23-story high rise with visitor and conference center, casino, printing facility, private and open plan offices with video conferencing equipment, three basement stories as well as a 4-story, flat-roofed redundant data processing center (1,400 m²), independent supply via UPS and ESPS systems as well as layout of all supply systems according to n+1 system
  • Sprinkler systems for basement floors 1 – 3 and high rise, total of 82,000 m², water treatment systems, booster stations, component activation and integrated cooling system in ceiling, 400,000 m³/h ventilation and exhaust systems with heat recovery, air conditioning with compressor units with 5MW cooling capacity.
  • Structured cabling CAT 7, outlets CAT 6
  • Security management system with access control, burglar alarm, and video surveillance
  • Medium voltage substation: 3 x 3,150 kVA Trafo
  • ESPS system: 2 x 2,100 kVA
  • Building management system with approx. 10,000 data points